HelpContactFor teachers and institutes
>_StemPy Lab
Mock TestsClasses

>_StemPy Lab

Learn. Solve. Code the solutions. Test yourself.

Live examsFree mock exams, timed and rankedEveryone starts together, and your score and rank come the moment it ends.See the exams →
Live examsInternational live exams are comingTell us which exam you want first. Timed practice papers are open now.See what is coming →

Learn

  • Physics
  • Chemistry
  • Mathematics
  • Biology
  • Python Programming
  • Statistics & Data Science
  • Computer Science
  • Space Science and Astronomy
  • Earth and Environmental Science
  • Classes
  • Groups

Practice

  • Problems
  • Quizzes
  • Mock Tests
  • Prepare for an Exam
  • Question Sets
  • Exams
  • Certificates
  • Python Labs
  • AI Practice Generator
  • Student-Created Tests

Community

  • Discussions
  • Resources
  • Notes
  • Glossary
  • Blog

Account

  • Log in
© 2026 senLearn. All rights reserved.HelpFor SchoolsAboutContactPrivacy PolicyTerms of UseRefund Policy
  1. Problems
  2. /A city must move 600 000 people out of a danger zone…
MediumEarth and Environmental ScienceHigh School (9–10)Natural HazardsNumericalConceptualICSE
+1 more exams
IGCSE
IGCSE

A city must move 600 000 people out of a danger zone…

StemPy LabContributed by StemPy Lab

Try it on paper first. A hint, the key idea and the worked solution are here when you need them.

A city must move 600 000600\,000600000 people out of a danger zone. The roads and trains can move 35 00035\,00035000 people each hour. The cyclone will arrive in 20 h20\ \text{h}20 h. (a) How many hours does the evacuation need? (b) How much spare time is there? (c) A bridge is closed, and the rate falls to 25 00025\,00025000 people an hour. How many hours does the evacuation need now? (d) What should the city plan, given the answer to (c)?

Check your answer

Work it out on paper, then type your number. The answer itself stays hidden.

h
h
h
Need a reminder? The key ideaShowHide

The time needed to move NNN people at a rate rrr people each hour is N/rN/rN/r. The spare time is the warning time less the time needed.

The worked solution

Check an answer or open a hint to unlock the worked solution.

Have you tried it?

Work it out on paper first. It is fine to get stuck or make a mistake: that is how we learn. When you are ready, go through the solution one step at a time, and check each step against your own.

Step 1. The time needed. 600 00035 000=17.1 h\dfrac{600\,000}{35\,000} = 17.1\ \text{h}35000600000​=17.1 h.

Step 2. The spare time. 20−17.1=2.9 h20 - 17.1 = 2.9\ \text{h}20−17.1=2.9 h.

Step 3. The closed bridge. 600 00025 000=24 h\dfrac{600\,000}{25\,000} = 24\ \text{h}25000600000​=24 h. This is 4 h4\ \text{h}4 h longer than the warning.

Step 4. The plan. The city should not depend on one route. It should leave early. It should start with the people in most danger or those who cannot move fast. It should add trains and buses, and open shelters near the zone for those who cannot get away.

Answer: 17.1 h17.1\ \text{h}17.1 h; 2.9 h2.9\ \text{h}2.9 h; 24 h24\ \text{h}24 h; start early and plan a second route.

Check. A drop in the rate from 35 00035\,00035000 to 25 00025\,00025000 is 29 %29\ \%29 %, and the time grows by 40 %40\ \%40 %, from 17.117.117.1 to 24 h24\ \text{h}24 h.

Log in to save this for later
← All Problems
← About 480 000 people live in a cyclone danger zone…A district can pay for only one of three measures… →
More onNatural Hazards

Discussion (0)

Log in to join the discussion.

Loading…

Learn it in

  1. Preparing, responding and recoveringRisk, Warning and Preparation: Managing Hazards

More on this topic

  1. A district can pay for only one of three measures…Hard
  2. About 480 000 people live in a cyclone danger zone…Easy
  3. An earthquake under the sea is 600 km from a coast…Hard
  4. An earthquake early warning system sends its alert 9 s after the earthquake begins…
Medium
  • A flood of a certain size has a return period of 100 years…Easy
  • All problems on this topic →