HelpContactFor teachers and institutes
>_StemPy Lab
Mock TestsClasses

>_StemPy Lab

Learn. Solve. Code the solutions. Test yourself.

Live examsFree mock exams, timed and rankedEveryone starts together, and your score and rank come the moment it ends.See the exams →
Live examsInternational live exams are comingTell us which exam you want first. Timed practice papers are open now.See what is coming →

Learn

  • Physics
  • Chemistry
  • Mathematics
  • Biology
  • Python Programming
  • Statistics & Data Science
  • Computer Science
  • Space Science and Astronomy
  • Earth and Environmental Science
  • Classes
  • Groups

Practice

  • Problems
  • Quizzes
  • Mock Tests
  • Prepare for an Exam
  • Question Sets
  • Exams
  • Certificates
  • Python Labs
  • AI Practice Generator
  • Student-Created Tests

Community

  • Discussions
  • Resources
  • Notes
  • Glossary
  • Blog

Account

  • Log in
© 2026 senLearn. All rights reserved.HelpFor SchoolsAboutContactPrivacy PolicyTerms of UseRefund Policy
  1. Python Labs
  2. /Should the project go ahead?
Earth and Environmental ScienceHardHigh School (11–12)Energy and Resources

Should the project go ahead?

You will write a small cost-benefit tool. It discounts each year's net benefit and decides whether a project is worth doing, first for its owner and then for society.

The idea. A sum FFF that comes ttt years from now is worth F/(1+r)tF/(1 + r)^tF/(1+r)t today. The net present value is the sum of these over the project's life, minus the cost now.

Your tasks.

  1. In present_value, return the value today of amount received years years from now.
  2. In npv, return the net present value of a project that costs cost_now and gives yearly every year for life years.
  3. In decide, return "build" if the social NPV (benefit minus harm each year) is positive, and "do not build" otherwise.

Run it first, just as it is. The checker at the end prints FAIL for each task. Then do the tasks one at a time, and run the program again after each one. A Hint appears under every check that still fails.

When every line says PASS, find the harm per year, to the nearest crore, at which the irrigation canal stops being worth building at a rate of 7 %.

StemPy LabContributed by StemPy Lab
python
Loading Python runtime…

A worked solution

Run your code once to unlock the worked solution.

Have you tried it?

Do the tasks in the editor first, and run the checker after each one. Its hints help when a check fails. When you are ready, compare your code with this solution.

Log in to save
← All Labs
← Rations for one laneA footprint calculator →
More onEnergy and Resources

Discussion (0)

Log in to join the discussion.

Loading…

Learn it in

  1. Welfare, externalities and cost-benefit analysisEnvironmental and Natural Resource Economics